Project timeline
- Planning phase: Completed by June 2010
- Design phase: July 2010 to December 2013
- Construction phase: April 2014 to December 2016
The project will require several actions by the water district Board to complete the anticipated work. Below is a list of the actions and when these items are estimated to be brought to the Board for approval.
Adopt Planning Study Report and authorize staff to proceed with design: June 2010
Certify Final Environmental Impact Report and Approve Project: December 2013